Resources - Distribution and Cost Dimensions
-
On the Resource form - Accounting tab, Cost Centers and Projects can be selected
-
The number of dimension fields displayed in the ProcessForce forms within SAP Business One is determined by the number of Cost Centers enabled in the SAP Business One General Settings.
-
Note the Resource Accounting combo-box, has been moved to this tab.
Operation Form
-
On the Operation form in Resources tab the Cost Centers and Project are displayed for each resource
-
Values are defaulting from the Resource form and can be changed if required
Routing Form
-
On the Routing form in Resources tab, the Cost Centers and Project are displayed for each resource
-
Values are defaulting from the Operation form and can be changed if required
-
When the operation is selected the default values are copied from the Operation definition, and can be changed if required
-
When the resource is selected the default values are copied from the Resource definition, and can be changed if required
Production Process Form
-
On the Production Process form in Resource section the cost centers and projects are displayed.
-
When the routing is selected, the default values are copied from the Routing definition, and can be changed if required.
-
When the operation is selected, the default values are copied from the Operation definition, and can be changed if required.
-
When the resource is selected, the default values are copied from the Resource definition, and can be changed if required.
Manufacturing Order Form
-
On Manufacturing Order form - Operations tab in Resource section the cost centers and resources are displayed.
-
According to the routing definition for the Bill of Material which was used to create the Manufacturing Order, the default values are copied, and can be changed if required.
-
When an operation is selected and added to the Manufacturing Order, the default values are copied, and can be changed if required.
-
When a resource is selected and added to the Manufacturing Order, the default values are copied, and can be changed if required.
Time Bookings Form
-
On Time Bookings form, the cost centers and resources are displayed.
-
According to Manufacturing Order definition the default values are copied, and can be changed if required.
Time Corrections Form
-
On Time Corrections form the cost centers and resources are displayed
-
According to Time Booking record the default values are copied, and can be changed if required
Postings
- When Time Booking or Time Correction document is saved we use set there Cost Centers and Project in created Journal Entry document
- Each cost center dimension from Time Bookings is saved in its respective counterpart in Journal Entry
- Cost centers are only saved for Sales and Expenditure type accounts
- Project is saved for every type account