Resources - Distribution and Cost Dimensions

  • On the Resource form - Accounting tab, Cost Centers and Projects can be selected

  • The number of dimension fields displayed in the ProcessForce forms within SAP Business One is determined by the number of Cost Centers enabled in the SAP Business One General Settings.

  • Note the Resource Accounting combo-box, has been moved to this tab.

    Distribution and Cost Dimensions

Operation Form

  • On the Operation form in Resources tab the Cost Centers and Project are displayed for each resource

  • Values are defaulting from the Resource form and can be changed if required

    Distribution and Cost Dimensions

Routing Form

  • On the Routing form in Resources tab, the Cost Centers and Project are displayed for each resource

  • Values are defaulting from the Operation form and can be changed if required

  • When the operation is selected the default values are copied from the Operation definition, and can be changed if required

  • When the resource is selected the default values are copied from the Resource definition, and can be changed if required

    Distribution and Cost Dimensions

Production Process Form

  • On the Production Process form in Resource section the cost centers and projects are displayed.

  • When the routing is selected, the default values are copied from the Routing definition, and can be changed if required.

  • When the operation is selected, the default values are copied from the Operation definition, and can be changed if required.

  • When the resource is selected, the default values are copied from the Resource definition, and can be changed if required.

    Distribution and Cost Dimensions

Manufacturing Order Form

  • On Manufacturing Order form - Operations tab in Resource section the cost centers and resources are displayed.

  • According to the routing definition for the Bill of Material which was used to create the Manufacturing Order, the default values are copied, and can be changed if required.

  • When an operation is selected and added to the Manufacturing Order, the default values are copied, and can be changed if required.

  • When a resource is selected and added to the Manufacturing Order, the default values are copied, and can be changed if required.

    Manufacturing Order Form

Time Bookings Form

  • On Time Bookings form, the cost centers and resources are displayed.

  • According to Manufacturing Order definition the default values are copied, and can be changed if required.

    Time Bookings Form

Time Corrections Form

  • On Time Corrections form the cost centers and resources are displayed

  • According to Time Booking record the default values are copied, and can be changed if required

    Time Corrections Form

Postings

  • When Time Booking or Time Correction document is saved we use set there Cost Centers and Project in created Journal Entry document
  • Each cost center dimension from Time Bookings is saved in its respective counterpart in Journal Entry
  • Cost centers are only saved for Sales and Expenditure type accounts
  • Project is saved for every type account

Distribution and Cost Dimensions