Test Protocols for Operation
It is possible to mark a Test Protocol as specific for a specific Operation (Test Protocol → Transactions tab → Operation).
You can assign a Test Protocol to an Operation on Production Process/Routing/Manufacturing Order (Operations tab).
Both ways will create a Quality Control Test, but there are some differences:
Scenario | Protocol Defined in Routing Based on Operation | General Settings > PF > QC - Create QC Document on MOR state | General Settings > PF > QC - Create QC Document for Operation on MOR state | Behavior |
---|---|---|---|---|
Create QC Based on MO | ❌ | ✔️ | ❌ | QC will be created based on MO. There won't be a link to Operation even though the operation is checked in test protocol |
Create QC Based on Operation | ✔️ | ❌ | ✔️ | QC will be created based on Operation. There will be a link between function and QC |
Create QC Based on MO and Operation | ✔️ | ✔️ | ✔️ | One for MO, one for operation linked will be created. Be careful with duplicated QCs. |
Based on Manufacturing Order:
Based on Manufacturing Order Operation:
Example
If there is a process, a kind of First Check before starting/completing the operation, Test Protocol should be defined in Routing to relate QC with Operation. There would be some requirements like blocking operation to start via PDC if QC - First check is not Passed.