Przejdź do głównej zawartości
Wersja: 3.0
informacja

You are currently viewing documentation for CompuTec ProcessForce 3.0, which is a plugin installed and managed through CompuTec AppEngine 3.0, built on .NET 8. If you are working with older environments, you may need the documentation for CompuTec ProcessForce 2.0: https://learn.computec.one/docs/processforce/2.0/.

Please note that CompuTec ProcessForce 2.0 will be supported only until December 31, 2026. After this date, the product will no longer receive regular support or maintenance updates. Read more

CompuTec AppEngine 3.0 introduces a new architecture, and all CompuTec components, including the CompuTec ProcessForce 3.0 plugin, must be updated together to ensure full compatibility.

Before starting your installation or upgrade process, we strongly recommend reviewing the CompuTec AppEngine 3.0 and CompuTec ProcessForce 3.0 documentation.

Orderless Production

Orderless Production lets you record production for several finished goods in one document. CompuTec ProcessForce creates the manufacturing orders and processes the related production transactions in the background, so you do not need to create each manufacturing order manually.

Before you start​

Before you begin, make sure that:

  • A numbering series is defined for the Orderless Production document.
  • Items and resources in the bill of materials (BOM) and in the production process are set to Backflushed. Backflushing records consumption automatically during processing.
  • Item costing is available for the items you want to produce. If an item cost is missing, processing fails.
  • (optional) An Orderless Production Template exists. A template fills the document for you, but you can also add new items to the list manually.

Create an orderless production template​

A template is a starting list of finished goods. When you select it in an Orderless Production document, CompuTec ProcessForce loads its items together with the related co-product and scrap rows.

To create an orderless production template, follow these steps:

  1. Go to Administration > Setup > Production > Orderless Production Template.

    alt text

  2. Create a new template.

  3. Enter the Code and Name of the template.

  4. Add the finished goods you want to include.

    alt text

  5. Save the template.

    Info

    You can edit finished goods rows in the template. Scrap and co-product rows are added automatically and are read-only, because CompuTec ProcessForce takes them from item costing.

Updated workflow​

Use this workflow in CompuTec ProcessForce 3.2610.1 and later.

Prepare a draft​

To prepare a draft, follow these steps:

  1. Go to Modules > Production > Manufacturing Order > Orderless Production.

    alt text

  2. In Template Code, select a template.

    alt text

  3. Review the loaded items, revisions, routings, and warehouses.

  4. (optional) Add the finished goods that are not in the template.

  5. Enter the produced quantity for each finished good.

    alt text

  6. Enter the Posting Date.

  7. (optional) In the Batch Number column, enter a batch number for a batch-managed finished good.

    note

    If you leave the Batch Number field empty, CompuTec ProcessForce creates the batch number from the configured batch numbering. If you enter a number, CompuTec ProcessForce uses it for the new batch when it creates the receipt.

  8. Make sure that in Status, you have selected Draft.

    alt text

  9. Click Add.

  10. Done! CompuTec ProcessForce saves the document. A draft creates no manufacturing orders and posts no transactions, so you can review the entries before processing.

    alt text

Start processing​

To start processing, follow these steps:

  1. Open the draft document.

  2. Check the finished goods, quantities, warehouses, posting date, and batch numbers.

  3. In Status, select Accepted.

    alt text

  4. Click Update.

    CompuTec ProcessForce assigns a Task ID and starts processing in the background. When processing succeeds, the manufacturing orders are created, the production issues and receipts are recorded, and the manufacturing orders are finished.

  5. To track the progress of processing, click the arrow next to Task ID.

    The progress view opens in the CompuTec AppEngine Launchpad.

    alt text

    info

    The progress view is labeled Saga progress. A saga is the sequence of steps that processes the document and handles failures. The steps are:

    • Creating Manufacturing Orders Step
    • Creating PickReceipts Step
    • Finishing Manufacturing Orders Step

    An exclamation mark next to a step means that the step failed. Refresh the document to see the latest status and error information.

  6. Your document is processed and you can see Success in the Status field.

    alt text

    info

    You can also skip the draft creation, and start processing when you create the document: select Accepted in Status before you click Add.

Review the result​

The document has the fields Status, State, and Task ID. Use Status to see the outcome of the document, and use Task ID to see how processing is going.

StatusMeaning
DraftThe document is saved for review. Processing has not started.
AcceptedThe document is submitted for processing. Open the Task ID progress view to see whether processing is still running.
SuccessProcessing completed successfully. The manufacturing orders are finished. Review the linked manufacturing orders and their production documents.
CanceledProcessing failed and the document is canceled. Review the error log before you create a new document.

Review linked documents​

In the Manufacturing Order column, each production row links to the manufacturing order that processing created.

alt text

Open a linked order to see its details and related documents.

alt text

Resolve a processing error​

If an error occurs while processing an Orderless Production document, CompuTec ProcessForce changes its status to Draft or Canceled, depending on when the error occurs.

  • Draft: If the error occurs before any Manufacturing Orders are created, the document returns to Draft. You can correct the error and process the same document again.

    alt text

  • Canceled: If Manufacturing Orders have already been created when the error occurs, the document is canceled. You cannot edit or process it again.

Correct an error in a draft document​

If the document returns to Draft, follow these steps:

  1. Refresh the Orderless Production document.

    alt text

  2. Check the Info field for details about the error, including the affected document lines and the reasons for the failure.

    alt text

  3. Correct the reported errors. For example, if an item has no cost, add the missing cost.

  4. Change the document Status to Accepted to process it again.

Transactions performed​

The following transactions are performed during the Orderless Production document creation:

ItemsBatch Traced Items (set to backflush) Based on FIFO, FEFO & FMFO rulesNon-Inventory Items (set to backflush)CoProducts (set to backflush)Scrap (set to backflush)Resource TimeFinished Products
Backflush✔️✔️✔️✔️✔️
Create Batch Number✔️✔️✔️
Create Journals✔️✔️✔️✔️✔️✔️✔️
Create Scrap & ByProducts✔️
Create CoProducts✔️
Create Finished Products✔️

What happens when a document is canceled?​

If processing fails after Manufacturing Orders have been created, CompuTec ProcessForce cancels the Orderless Production document and rolls back the related production transactions.

alt text

The following information remains available for reference:

  • Manufacturing Orders created during the failed process remain in the system with the status Closed.
  • Each affected Manufacturing Order contains a remark explaining that it was closed because of a processing error, along with details that may help you create a new Orderless Production document.
  • Production transactions and related documents created during the failed process are rolled back.
info

You can find a reference to the original Orderless Production document on the Other tab of the affected Manufacturing Orders.

alt text

note

If the problem continues, visit CompuTec Support Portal. Include the Orderless Production document number, Task ID, error details from the Info field, and the numbers of the affected Manufacturing Orders.

Previous workflow​

This section applies to CompuTec ProcessForce 3.0 releases earlier than CompuTec ProcessForce 3.2610.1 and to CompuTec ProcessForce 2.0. These versions have no Status, Task ID, or Batch Number fields, and no error log.

For CompuTec ProcessForce 2.0, you can also read the CompuTec ProcessForce 2.0 documentation.

Configure orderless production​

To configure orderless production, follow these steps:

  1. Define a document series for the Orderless Production Document in the master data.

    Document Numbering

    info

    For detailed instructions on setting up a document series, check our document numbering guide

  2. In the bill of materials and in the production process, set all items and resources to Backflushed.

  3. (optional) Create an Orderless Production Template that lists the items you want to produce. When you select the template, CompuTec ProcessForce fills the document, including co-products and scrap.

Run orderless production​

To run orderless production, follow these steps:

  1. Open the Orderless Production Document.

  2. Select a template, or enter the items manually. CompuTec ProcessForce adds the related co-product and scrap rows automatically.

    Orderless Production Template

  3. Enter the posting date and the produced quantity.

  4. Confirm the document.

    Orderless Production Document

CompuTec ProcessForce creates a manufacturing order in the background and runs it from release to closure.

info

The Orderless Production Document serves as the central point for recording production activities. Users can select a predefined template or manually enter items to be produced. When an item has associated CoProducts and Scrap, these are automatically included.

The user inputs the posting date and the quantity produced, then confirms the entry. This action triggers a manufacturing order in the background, executing a complete production cycle from release to closure.

Transactions performed​

The following transactions are performed:

ItemsBatch Traced Items (set to backflush) Based on FIFO, FEFO & FMFO rulesNon-Inventory Items (set to backflush)CoProducts (set to backflush)Scrap (set to backflush)Resource TimeFinished Products
Backflush✔️✔️✔️✔️✔️
Create Batch Number✔️✔️✔️
Create Journals✔️✔️✔️✔️✔️✔️✔️
Create Scrap & ByProducts✔️
Create CoProducts✔️
Create Finished Products✔️